EIA
2020-07-06 18:41:43
- EIA
- through EIA planners try to harmonise dev activities w/ environmental concerns
- can prevent future liabilities or expensive alteration in project design
- objective is to foresee potential env problems, identify key impacts issues
- ==started in 1976-77 for river valley projects==
EIA in India
Section titled “EIA in India”Screening
Section titled “Screening”- to see whether a project requires env clearance
- based on criteria like scales on investment, type of dev, location of dev
Scoping
Section titled “Scoping”- process of detailing the terms of reference of EIA
- done by a consultant, MoEFCC has published sector-wise guidelines
- Quantifiable impacts are assessed and non quantifiable impacts such as aesthetic value determined
Baseline Data
Section titled “Baseline Data”- describes existing environmental status
- primary data should be monitored and supplemented by secondary ones
Impact Prediction
Section titled “Impact Prediction”- way to map env consequences, predict all factors and uncertainities that would arise
- Impact on air, noise, water, land, biological, socio economic and impact on economic status
Assessment of Alternatives, Delineation of Mitigation Measures and EIA Report
Section titled “Assessment of Alternatives, Delineation of Mitigation Measures and EIA Report”- for every project possible alternative be identified and env attributes of it compared to the original project
- should also consider the no project options, alternatives should then be ranked
- mitigation plant for the selected option supplemented with an Env Management Plan : to manage clearance conditions
- EIA report should provide info on various env scenarios w/ and w/o the project
Public Hearing
Section titled “Public Hearing”- public be informed and consulted after completion of EIA report
- consisting of bonafide local residents, local associations, env groups etc
Environment Management Plan
Section titled “Environment Management Plan”- should include delineation of mitigation and compensation measures, unmitigated impacts
- physical planning, time schedule, location etc for mitigation and compensation sys in place
- Delineation of mitigation plan
Decision Making
Section titled “Decision Making”- consultation b/w project proponenets and EIA authority
- decision on env clearance
Monitoring Clearance Conditions
Section titled “Monitoring Clearance Conditions”- during both construction and operation phases of a project
- to ensure commitments are complied and to observe prediction of EIA were correct or not
- corrective action when there is deviation from prediction
Components of EIA
Section titled “Components of EIA”- Rapid EIA differs from comprehensive in terms of time scale, done to show if a comprehensive EIA is req or not
Air Env
Section titled “Air Env”- determinatinon of impact zone, monitor existing status of ambient air quality
- monitor site specific meteorological data, estimate quantities of air emission
- predict changes in it
Noise Env
Section titled “Noise Env”- monitor present levels and predict future noise levels
- identify imapct due to it, recom mitigation measures
Water Env
Section titled “Water Env”- study of existing ground and surface water resources wrt quantity and quality
- predict impact, quantify and characterisation of waste
- evaluate proposed pollution prevention, predict impact of effluent discharge, assess feasibility of water recycling
Biological Env
Section titled “Biological Env”- assess flora and fauna, potential damage to both terrestrial and marine flora and fauna
- predict biological stress within impact zone, delineate mitigation measure to prevent/ reduce damage
Land Env
Section titled “Land Env”- studies on soil characterstics, estimate on impact of project on land use, landscape topography
- identification on potential utility of treated effluent, estimation and characterisation of solid wastes
Socio-economic and Health Env
Section titled “Socio-economic and Health Env”- collection of demographic, epidemiological data, projection of anticipated changes in socio-economic and health
- assess impact on historical and cultural and archaeologica sites
- assess rehab requirement w/ special emphasis on scheduled areas
Risk Assessment
Section titled “Risk Assessment”- Hazard identification, Maximum Credible Accident MCA to id potential hazardous scenarios
- Analysis of possible failures and accidents resulting in fires
- Hazard and Operability HAZOP studies
- Assessment of risk, preparation of o site and off site DM plan
Environment Management Plant
Section titled “Environment Management Plant”- Delineation of mitigation measures, monitoring scheme for compliance
- Delineate implementation plan viz scheduling and resource allocation
EIA Notification of 2006 #important #Act
Section titled “EIA Notification of 2006 #important #Act”- It has decentralised the env cliearance projects by ==classifying them into Categories A and B==
- ‘Category A’ projects are ==appraised at national level== by Impact Assessment Agency (IAA) and the Expert Appraisal Committee (EAC).
- Category B projects are apprised at state level by State Level Environment Impact Assessment Authority (SEIAA) and State Level Expert Appraisal Committee (SEAC).
- Category A projects ==require mandatory environmental clearance and thus do not undergo the [[#Screening]] process==
- Category B projects ==undergoes [[#screening]]== process and they are ==classified into two types B1 and B2==.
- B1 requires mandatory environmental clearance. ==B2 do not require EIA==.
Key Element of Initial Project Description and Scoping
Section titled “Key Element of Initial Project Description and Scoping”- for key projects, Initial Project Description IPD to enable project screening and scoping -> this would facilitate reviewers task
- IPD should provide - location and land use, details of project, outlining key element of project, offsite and onsite activities
Siting/ Project Location Critera per MoEF
Section titled “Siting/ Project Location Critera per MoEF”- prime agricultural land/forest land may not be converted to industrial site
- land acquired be min, space for storing solid waste, layout should conform to landscape of [[3.1 Climate Change and Impact on India#Coastal Regulation Zone 2011 notification - are under EPA 1986|CRZ norms]]] should be followed
- project location be reviewed for ambient air, critically polluted ares, natural disaster prone areas etc
Procedure for Public Hearing
Section titled “Procedure for Public Hearing”- coys that want public hearing for clearance of projects should submit to SPCB #important
- SPCB gives notice to be published in 2 newspapers along mentioning the date, time and place of public hearing
- suggestions from public within 30 days from date of publication of notification, can also make oral/ written suggestion
- Public hearing panel could have rep of SPCB, DC, rep of State gov, max 3 reps from local bodies viz Municipalities, panchayats etc
Drawbacks of EIA in India
Section titled “Drawbacks of EIA in India”- several projects not listed because they are not listed in Schedule 1 or do not have high enough investmemt
- teams formed for conducting EIA lacks expertise, lack of exhaustive ecological and socio-economic indicators for IA
- Public hearing not being taken at early stage, no of projects not included in mandatory public hearings, indigenous knowledge of people not respected during EIA
- Reports mostly incomplete, ignore or omits significant info, many reports are base only on a single season
- reports made for clearance, unbiased review is missing, bending of rules common
- documents are bulky, technical, sometimes fraudulently made
- No accredition of EIA consultants
- EMP for strategic industires viz nuclear are kept confidential, details regarding effectivenes and implementation not provided, emergency preparedness plans not discussed
- Independent, sector wide EIA needed, creation of info desk, creation of centralised baseline data bank
- all projects where there is a significant alteration of ecosys should compulsorily go through env clearance, no industrial act in ecologically sensitive area
- Public hearing for most projects
- Focus shifts from utilisation of exploitation to conservation of ecosys
- impact on agribiodiversity, and traditional knowledge should be included
- clearly state adverse impact, studies should be carried for at least 1yr
- State amd Centre should make list of credible and independent competent agencies along w/ national level accredition
- prior informed consent of local communities be made mandatory, language for specifying condition be made clear and specific
- executive committee be replace by expert comm
- automatic withdrawal of clearance if condition of clearance not met, robust monitoring mechanism estd by state dept
- Judicial upheaval of NGT
- Capacity building
[[Static - Conservation, Environmental pollution and degradation, environmental impact assessment#PARIVESH |PARIVESH]]
Environment Supplement Plan ESP
Section titled “Environment Supplement Plan ESP”- undertaken ==by an alleged violator of EIA 2006== act to get clearance for their project
- can continue their activity by paying financial penalty
Negatives
Section titled “Negatives”- attempt to legalise violations, defeats the purpose of EIA
- indirectly allows pardoning of violations, escape mechanism for violators